What is the probability if the company wants the project completed in more than 32 weeks?

You should spend 80 min. to complete the following three problems (open-book, NO open-note):
Problem 1 (30 Points): An engineer is asked to provide the company with an estimated total cost for both a new and used vehicle over the 5 year test period. A new vehicle costs $20,000 and has an annual maintenance and operating cost of $15,000. A used vehicle costs $10,000 and has an annual maintenance and operating cost of $19,000. It is also estimated that the new car will have a salvage value of $8,000 and the used car will have a salvage value of $4,000. Determine the total present value of costs as a discount rate of 10%. (Show all of your work)

Problem 2 (40 Points): Shown below are the PERT schedule and the precedence relationships among the activities required to complete a project.
⦁ Setup the project activity network diagram for the following relationships in the table and determine the critical path.
⦁ What is the probability if the company wants the project completed in more than 32 weeks?

Are you looking for a similar paper or any other quality academic essay? Then look no further. Our research paper writing service is what you require. Our team of experienced writers is on standby to deliver to you an original paper as per your specified instructions with zero plagiarism guaranteed. This is the perfect way you can prepare your own unique academic paper and score the grades you deserve.